Black Friday Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65pass65

Good News !!! ISEB-PM1 BCS Foundation Certificate in IS Project Management is now Stable and With Pass Result

ISEB-PM1 Practice Exam Questions and Answers

BCS Foundation Certificate in IS Project Management

Last Update 1 day ago
Total Questions : 625

BCS Foundation Certificate in IS Project Management is stable now with all latest exam questions are added 1 day ago. Incorporating ISEB-PM1 practice exam questions into your study plan is more than just a preparation strategy.

ISEB-PM1 exam questions often include scenarios and problem-solving exercises that mirror real-world challenges. Working through ISEB-PM1 dumps allows you to practice pacing yourself, ensuring that you can complete all BCS Foundation Certificate in IS Project Management practice test within the allotted time frame.

ISEB-PM1 PDF

$43.75
$124.99

ISEB-PM1 Testing Engine

$50.75
$144.99

ISEB-PM1 PDF + Testing Engine

$63.7
$181.99
Question # 1

When does risk monitoring and control occur?

Options:

A.  

At project initiation

B.  

During work performance analysis

C.  

Throughout the life of the project

D.  

At project milestones

Discussion 0
Question # 2

Management reserves are normally defined as a % of the total budget. As a project progresses, the project manager wants the $ value of management reserve to _____, whereas the customer wants the management reserve to _____.

Options:

A.  

Increase, increase.

B.  

Increase, decrease.

C.  

Remain the same, return to customer.

D.  

Decrease, increase.

E.  

Decrease, decrease.

Discussion 0
Question # 3

To complete performance index (TCPI) is represented by which of the following?

Options:

A.  

BAC - EV/BAC - AC

B.  

A measure of the value of work completed compared to the actual cost or progress

C.  

A measure of progress achieved compared to progress planned

D.  

AC + (BAC - EV)

Discussion 0
Question # 4

The widget production project is well underway. The requirements are clear that each widget must weigh between 0.320 and 0.325 ounces. The first day of test production resulted in 1247 widgets. Of the widgets inspected, 47 percent fell within the acceptable weight range. This is an example of:

Options:

A.  

Control limits.

B.  

Quality assurance.

C.  

Control charting.

D.  

Corrective action.

Discussion 0
Question # 5

In an activity-on-node diagram, the nodes represent:

Options:

A.  

Work packages.

B.  

Activities.

C.  

Dependencies.

D.  

Discretionaries.

Discussion 0
Question # 6

A problem occurs on an activity with free float and the project manager has extended its duration.

What is MOST likely to be affected?

Options:

A.  

Project duration

B.  

Resource schedules

C.  

Project scope management plan

D.  

The latest start for the successor activity

Discussion 0
Question # 7

What is the expected activity cost for a project having a most likely cost of $140, a best case scenario of $115, and a worst case scenario of $165?

Options:

A.  

$115

B.  

$138

C.  

$140

D.  

$165

Discussion 0
Question # 8

In which of the following is the cost of risk hidden by the contractor?

Options:

A.  

Fixed Price Plus Incentive

B.  

Firm Fixed Price Contract and Fixed Price Plus Incentive

C.  

Firm Fixed Price Contract

D.  

Cost Plus Percentage of Cost

E.  

Cost Plus Fixed Price

Discussion 0
Question # 9

A Project Management Office (PMO) manages a number of aspects, including what?

Options:

A.  

Project scope, schedule, cost, and quality of the products of the work packages

B.  

Central coordinator of communication management across projects, and for the delivery of specific project objectives, organization opportunity assessment

C.  

Assigns project resources to best meet project objectives

D.  

Overall risk, overall opportunity and interdependencies among projects

Discussion 0
Question # 10

Which of the following provides a comprehensive and consistent method of controlling the project and ensuring its success?

Options:

A.  

Stakeholder management

B.  

Monitoring and controlling

C.  

Project governance

D.  

Project management methodology

Discussion 0
Get ISEB-PM1 dumps and pass your exam in 24 hours!

Free Exams Sample Questions

sale-70-410-exam    | Exam-200-125-pdf    | we-sale-70-410-exam    | hot-sale-70-410-exam    | Latest-exam-700-603-Dumps    | Dumps-98-363-exams-date    | Certs-200-125-date    | Dumps-300-075-exams-date    | hot-sale-book-C8010-726-book    | Hot-Sale-200-310-Exam    | Exam-Description-200-310-dumps?    | hot-sale-book-200-125-book    | Latest-Updated-300-209-Exam    | Dumps-210-260-exams-date    | Download-200-125-Exam-PDF    | Exam-Description-300-101-dumps    | Certs-300-101-date    | Hot-Sale-300-075-Exam    | Latest-exam-200-125-Dumps    | Exam-Description-200-125-dumps    | Latest-Updated-300-075-Exam    | hot-sale-book-210-260-book    | Dumps-200-901-exams-date    | Certs-200-901-date    | Latest-exam-1Z0-062-Dumps    | Hot-Sale-1Z0-062-Exam    | Certs-CSSLP-date    | 100%-Pass-70-383-Exams    | Latest-JN0-360-real-exam-questions    | 100%-Pass-4A0-100-Real-Exam-Questions    | Dumps-300-135-exams-date    | Passed-200-105-Tech-Exams    | Latest-Updated-200-310-Exam    | Download-300-070-Exam-PDF    | Hot-Sale-JN0-360-Exam    | 100%-Pass-JN0-360-Exams    | 100%-Pass-JN0-360-Real-Exam-Questions    | Dumps-JN0-360-exams-date    | Exam-Description-1Z0-876-dumps    | Latest-exam-1Z0-876-Dumps    | Dumps-HPE0-Y53-exams-date    | 2017-Latest-HPE0-Y53-Exam    | 100%-Pass-HPE0-Y53-Real-Exam-Questions    | Pass-4A0-100-Exam    | Latest-4A0-100-Questions    | Dumps-98-365-exams-date    | 2017-Latest-98-365-Exam    | 100%-Pass-VCS-254-Exams    | 2017-Latest-VCS-273-Exam    | Dumps-200-355-exams-date    | 2017-Latest-300-320-Exam    | Pass-300-101-Exam    | 100%-Pass-300-115-Exams    |
http://www.portvapes.co.uk/    | http://www.portvapes.co.uk/    |