Scaled Professional Scrum (SPS) Exam
Last Update 4 days ago
Total Questions : 40
Scaled Professional Scrum (SPS) Exam is stable now with all latest exam questions are added 4 days ago. Incorporating SPS practice exam questions into your study plan is more than just a preparation strategy.
SPS exam questions often include scenarios and problem-solving exercises that mirror real-world challenges. Working through SPS dumps allows you to practice pacing yourself, ensuring that you can complete all Scaled Professional Scrum (SPS) Exam practice test within the allotted time frame.
Scenario C: Dependencies and Product Backlog items
During Nexus Sprint Planning, representatives from each of the 9-member Scrum Teams
identify many dependencies. This makes it hard for them to choose the work they could pull
into their individual teams for the next Sprint. No matter how they reorganize the Product
Backlog items, they continually find more or new dependencies.
What should the Scrum Teams do to effectively deal with their dependencies?
(choose the best answer)
The Scrum Teams in a Nexus find they have simply too much work each Sprint to do to deliver
a valuable and useful Increment. What could they try to improve their ability to produce an
Increment for the next Sprint?
(choose the best answer)
Scenario B: Six Team Nexus with complex dependencies
A six team Nexus is developing a complex product, with different parts of the product that only
certain Scrum Teams can work on. In fact, there are some highly specialized individuals outside
the Nexus that are required for some of the work. In past Sprints the Nexus encountered
challenges dealing with the many dependencies between Scrum Teams.
Which of the following practices could this Nexus try in order to conduct Nexus Sprint Planning
more effectively?
(choose the best two answers)
True or False: Using Scrum ensures that adding more resources to a product delivery effort
proportionally increases the value delivered.
True or False: When multiple Scrum Teams are working together on the same product, each
team should maintain a separate Product Backlog.
Scenario B: Six Team Nexus with complex dependencies
A six team Nexus is developing a complex product, with different parts of the product that only
certain Scrum Teams can work on. In fact, there are some highly specialized individuals outside
the Nexus that are required for some of the work. In past Sprints the Nexus encountered
challenges dealing with the many dependencies between Scrum Teams.
Which of the following two strategies would be most effective in dealing with their
dependencies?
(choose the best two answers)
During Cross-Team Refinement, the ordered Product Backlog (1 through 9) is mapped out so
the Nexus can visualize dependencies. For example, PBI 5 for Team Orange is dependent on
Team Red completing PBI 1.
All else being equal, which PBI is most concerning?
(choose the best answer)
True or False: Scrum Teams must report back to the Nexus Integration Team right after their individual Daily Scrums.
TESTED 27 Nov 2024
Hi this is Romona Kearns from Holland and I would like to tell you that I passed my exam with the use of exams4sure dumps. I got same questions in my exam that I prepared from your test engine software. I will recommend your site to all my friends for sure.
Our all material is important and it will be handy for you. If you have short time for exam so, we are sure with the use of it you will pass it easily with good marks. If you will not pass so, you could feel free to claim your refund. We will give 100% money back guarantee if our customers will not satisfy with our products.