Got an interesting story today. A local hospital recently had a power outage, but its generator failed to start. Leading to a lot of difficulty on the ICU, with nurses and assistants having to do manual ventilation for 1 hour, difficulties in surgery, etc.
Realising the generator was hosed, they arranged for a rental. A couple of days later a 1 MVA generator on a flatbed was delivered, and after about 2 days the electricians eventually get it wired in.
Things worked well, until the next weekend, when the power went out again. The generator did start, but power to the UPS protected circuits was lost. When it eventually came back a whole bunch of equipment connected to the UPS was toast. Not much medical equipment was damaged, as it tended to have internal UPSs, so was not on the enterprise UPS. However, a whole bunch of servers, switches and SANs were totally fried. It took a few days to get most of the critical apps back on line on new servers after restoring from tape.
The UPS is also toast, so is currently bypassed.
Apparently, the problem was that the UPS had not been correctly connected to the temp generator. When the generator started, the dual-conversion UPS failed to charge. An electrician then manually switched it to bypass mode. Unforutnately, this was a UPS bypass switch, which is make-before-break; normally this would only be used with the UPS correctly synchonized with the mains frequency, but due to the manual rewiring the UPS couldn't sync with the generator. As a result, there was an unsynchronized parallel connection between inverter and generator.
The result: a lot of very expensive magic smoke.
Realising the generator was hosed, they arranged for a rental. A couple of days later a 1 MVA generator on a flatbed was delivered, and after about 2 days the electricians eventually get it wired in.
Things worked well, until the next weekend, when the power went out again. The generator did start, but power to the UPS protected circuits was lost. When it eventually came back a whole bunch of equipment connected to the UPS was toast. Not much medical equipment was damaged, as it tended to have internal UPSs, so was not on the enterprise UPS. However, a whole bunch of servers, switches and SANs were totally fried. It took a few days to get most of the critical apps back on line on new servers after restoring from tape.
The UPS is also toast, so is currently bypassed.
Apparently, the problem was that the UPS had not been correctly connected to the temp generator. When the generator started, the dual-conversion UPS failed to charge. An electrician then manually switched it to bypass mode. Unforutnately, this was a UPS bypass switch, which is make-before-break; normally this would only be used with the UPS correctly synchonized with the mains frequency, but due to the manual rewiring the UPS couldn't sync with the generator. As a result, there was an unsynchronized parallel connection between inverter and generator.
The result: a lot of very expensive magic smoke.